The construction project started in 2014 and the gas-fired combined-cycle power plant was connected to the Chilean grid in June 2016.
PUBLICITÉ
Samsung C&T and KOSPO composed the consortium for the project. They hold respectively 35% and 65%. Samsung Engineering has secured the EPC contract.
In 2013, the companies have reached a 25 year power purchase agreement with the Chilean arm of BHP Biliton to supply electricity to its copper mines, including the Escondida project.
The Kelar plant has cost $600M.