Simultaneous lifting with 14 Manitowoc Grove cranes

MARY BRUNE, LE 27 MARS 2017
Archiver cet article
Newsletters
Simultaneous lifting with 14 Manitowoc Grove cranes
In Antwerp, Belgium, Aertssen Kranen have used 14 Manitowoc Grove cranes to perdorm a simultaneously lift of a pipeline for an industrial plant project.

Each of the Grove crane lifted a 6.1 tons section of the pipeline.

PUBLICITÉ
The 14 Grove cranes selected for the lift are all from the all-terrain range:


   Seven GMK3055s


  Three GMK4080s


  Two GMK5095s


  Two GMK5130-2s

The company had experiences with multi-lift operations up to 11 cranes that involved pipelines up to 250 m, but lifting a 14-section pipe with joints was a first for them.




PARTAGER :
Toute l'information de cette rubrique est dans : BTP Magazine
Le magazine de toute l'actualité des constructeurs, distributeurs et loueurs de matériels.
Découvrir nos newsletters →
À LIRE ÉGALEMENT
Un nettoyeur de câble simplifie la maintenance des grues Grove
Un nettoyeur de câble simplifie la maintenance des grues Grove
Une édition 2025 des trophées grues à tour pleine de saveurs
Une édition 2025 des trophées grues à tour pleine de saveurs
Potain (Manitowoc) met fin à son contrat de distribution avec Uperio France
Potain (Manitowoc) met fin à son contrat de distribution avec Uperio France
La grue a désormais son fil à la patte
La grue a désormais son fil à la patte
TOUS LES ARTICLES BÂTIMENT - GROS OEUVRE
Les plus lus